Pasadena Water Main Work Brings Daytime Lane Closures at Raymond and Fillmore
Pasadena Water and Power is conducting a water-main replacement on Fillmore Street near Raymond Avenue. The project involves daytime construction from 9 a.m. to 4 p.m., starting Aug. 17, which will cause partial lane closures at the intersection. The overall work is expected to finish by the end of August, accelerating the original mid-September timeline.