- Riverfront Data Center In McKinley Park Revives Expansion Plans But Faces Delay
QTS Data Center in McKinley Park is reviving its expansion plans for a Chicago Riverfront facility but faces delays due to a voided permit from inactivity. The proposed expansion includes new buildings and amenities, though concerns about environmental impact and infrastructure strain have prompted calls for stricter regulations.
- How a nine-month data center moratorium in SC impacts projects under construction
York County Council in South Carolina voted for a nine-month moratorium on new data centers to study their impact on resources and infrastructure. The moratorium's effect on the QTS Data Center project under construction, including nine buildings at Lake Wylie, remains unclear, as legal advisors determine if existing approvals or 'vested rights' exempt it. Community members and officials seek clarity ahead of council meetings on June 29 and July 13.