- Ohio has blocked a lot of wind and solar. Its residents pay the price.
Ohio has blocked over 5.3 gigawatts of solar and wind projects in the past 12 years, including the 800-megawatt Oak Run Solar Project, leading to higher electricity prices and missed opportunities to reduce emissions. State laws and court decisions, such as a 2014 wind turbine setback rule and Senate Bill 52, have restricted renewable energy development while allowing fossil fuel and nuclear projects.
- Ohio has blocked a lot of wind and solar. Its residents pay the price.
The Ohio Supreme Court blocked a permit for the state’s largest solar installation, the 800-megawatt Oak Run Solar Project, reversing part of the state siting board’s prior approval but leaving a potential pathway for completion. The decision highlights ongoing challenges for renewable energy projects in Ohio.
- Catching Our Eye News Roundup, May 29, 2026
The article discusses potential Medicaid changes due to fraud allegations, Ohio cities implementing short-term rental regulations, Cleveland's opposition to hyperscale data centers, a legal review of a solar project on Bill Gates' land, and a Justice Department investigation into E. Jean Carroll's lawsuit against Trump.
- Catching Our Eye News Roundup, May 27, 2026
The Ohio Supreme Court ruled that a Madison County solar project requires more information on visual impacts before approval. A U.S. Forest Service research station in McArthur is under evaluation for closure as part of a national reorganization. Notre Dame College in Northeast Ohio, which closed due to financial issues, has sold its campus.