Metropolitan Council
Coverage of Metropolitan Council in the Nexus archive.
- Documenters report: Officials shrink Blue Line budget gap from $279 million to $89 million
The Blue Line Extension Project Decision Board approved $190 million in budget reductions, shrinking the funding gap from $279 million to $89 million. Key cuts included removing a pedestrian bridge and adjusting parking spaces, while shifts to local funding sources reduced finance charges. The board discussed contingency funds and potential sales tax funds to address the remaining gap.
- Counterpoint: Bus rapid transit is a better alternative for the north metro
The article argues that a Bus Rapid Transit (BRT) network is a more cost-effective and beneficial alternative to the proposed $3.58 billion Blue Line Extension light-rail project for the north metro. A Metropolitan Council study suggests that multiple BRT lines could serve more residents, reduce costs, and provide greater mobility than a single light-rail line, challenging the current debate between one BRT and one rail option.
- Ex-Metro Transit chief discriminated against female employees, report finds
An investigative report found former Metro Transit Police Chief Ernest Morales engaged in gender-based discrimination against female employees, made sexual and derogatory comments, and violated body camera policy. The report, conducted by Nilan Johnson Lewis, revealed a hostile work environment and retaliation against subordinates, leading to his bar from policing in May.
- Community reacts to growing Blue Line extension budget and timeline
Metropolitan Council and Hennepin County officials held the first community meeting since the Blue Line Light Rail Extension project's budget increase was announced. The meeting addressed community reactions to the growing budget and timeline for the project.
- Fisk University ‘aware of the proliferation of environmentally harmful data centers’ as it vows to ‘do no harm’
Fisk University faces community backlash over plans for a 70,000-square-foot data center on its campus, citing environmental and public health concerns. The university claims it is prioritizing 'do no harm' principles and collaborating with Nashville leaders to address potential impacts, as the city considers regulatory measures for data centers.
- Met Council report finds ballooning costs for Blue Line
The Met Council reported a $336 million cost increase for the Blue Line extension to Brooklyn Park, totaling $3.6 billion, sparking debate among officials. The Minneapolis Park and Recreation Board faces opposition over closing Minnehaha Off-Leash Dog Park due to archaeological concerns, while a Minneapolis council member highlights safety issues at Heritage Park affordable housing.
- Train vs. bus debate fueled by new report on Blue Line Extension
A new report by the Metropolitan Council compares a $3.58 billion light rail extension (Blue Line) with a $120 million bus rapid transit alternative, sparking debate among supporters and opponents. Rep. Jon Koznick advocates for halting the light rail project due to cost concerns, while Hennepin County Commissioner Jeff Lunde emphasizes the necessity of the light rail for transit-dependent communities.
- Some riders worried about upcoming Metro Mobility schedule changes
Metro Mobility riders are concerned about upcoming July 1 service changes aligned with Metro Transit bus route updates. The Metropolitan Council stated the adjustments are routine and required by federal law to maintain paratransit service within three-fourths of a mile of bus routes, but riders fear reliability issues in suburban areas.
- Blue Line expansion price tag goes up as new cost study is due
The Blue Line expansion project's estimated cost has risen to $3.6 billion, sparking debate between supporters like Claudia Fuglie, who advocates for accessible transit, and opponents like Rep. Jon Koznick, who question the financial feasibility. A new study comparing the light rail expansion to an expanded bus system is expected soon.
- Cost of $3B Blue Line Extension project increases again — by over $330M
The Blue Line Extension project's cost has increased by $336 million, raising the total projected cost to nearly $3.6 billion. The Metropolitan Council attributed the increase to project scope changes and additional contingency, with construction starting in 2027 and service delayed until 2033.