CBG plant at Brahmapuram to reach full capacity of 150 tonnes by third week of August, says BPCL-KR
BPCL-KR states its CBG plant at Brahmapuram will reach full capacity of 150 tonnes by the third week of August but is currently undergoing stabilization. The Kochi Corporation has criticized the plant for failing to process the promised volume and is preparing to petition the Chief Minister, while BPCL-KR cites operational and waste quality issues as causes for the delay.