HEALTHVTDIGGER
Asbestos complicates Royalton mill demolition
The demolition of a former grain mill in South Royalton, Vt., is delayed due to asbestos found on the site, requiring proper removal before proceeding. The property owner, Eric Jacobs, failed to complete a required asbestos assessment, prompting state intervention. Residents express frustration over delays and lingering odors from the site.
Mentioned
Related Signal
Adjacent reporting
- DEP issues stop work order for Roosevelt Island steam plant demolition
- NYC’s demolition of iconic steam plant used in Marvel series violated its own asbestos rules: records
- Fayette County to demolish burned portion of historic former school building
- Pilsen residents warn of toxic metals from metal scrapper, ask Pritzker to slow permit renewal
- Littleton neighbors demand for former Southbridge Swim and Racquet Club property to be cleaned up
- Defiant last resident of abandoned tower block once home to 75 families blocks demolition after refusing to leave