Engineer behind buckled high-rise says crucial reinforcing steel was 'never installed'
An engineer stated that crucial reinforcing steel was never installed in a buckled high-rise, despite construction plans specifying its inclusion. The issue occurred at the former Pfizer headquarters building, where structural columns failed.